Mum and Dad are quite a bit ahead of us now as their roof was finished about three weeks ago so the plasterers could start.
The plasterer will be finished in their house this week and is moving onto ours afterwards.
The underfloor heating is now down with the screed on top.
John, the decorator, starts next weekend and the floor tiles are arriving so that they can be fixed in place. All moving very fast...
Downstairs toilet/cloakroom:
Study with insulation on floor ready for underfloor heating:
Boiler in plastered utility room and pipework for underfloor heating:
The very tall lounge ceilings being plastered:
Exposed hallway with removed balistrades on landing - it's like a adventure challenge crossing that - very scary!
Underfloor heating pre-screed in kitchen:
And in lounge: